Dollar General Distribution Center
Owner: Dollar General
Engineer: LAN Lockwood, Andrews, Newnam, Inc.
Cost: $12.4 Million
In September 2014, Yantis Company was awarded the mass grading and utilities contract for Dollar Generalās new distribution center. Located just south of IH-10 on Foster Road, the site spans over 100 acres. The project was designed by Lockwood, Andrews & Newnam (LAN). Yantis is working directly for Dollar General on this project.
Yantisā contract includes: 370,000 cy of excavation; over 496,000 cy of embankment; 275,000 cy of cement treated pad; 210,000 sy of 12ā cement treated subgrade. Yantis installed over 30,000 lf of storm drain, sewer, and water pipe as well as the dry electric package.
The construction of the 1 million square foot pad began 9/2/14 and was completed on 12/5/14, 10 days ahead of schedule.
About Yantis Company
- Senior Management
- Our History
- Why work with Yantis?
- Career Opportunities
- Safety Program
Our Services
- Commercial / Industrial
- Single Family Developments
- Asphalt Maintenance
- Public Infrastructure
- Rock Milling / Trenching
- Curb / Concrete Division
Our Services
Copyright 2018 Yantis Company, All Rights Reserved.