BV Carrier Warehouse
Owner: Tom Leiser of Bandera Ventures
Engineer: Pape-Dawson Engineers
Cost: $1.3 Million
Located on Applewhite Road in South San Antonio, Yantis was the site contractor for the BV Carrier Warehouse project. The site included a 513,000 sf tiltwall facility with a 302,000 sf storage pad plus 45 acres of associated sitework and a turn lane off Applewhite Road.
The project which ran on an extremely expedited schedule included 400,000 cy of excavation and embankment. In the grading phase Yantis had over 25 personnel and machinery onsite working 7 days a week to meet the owner’s schedule.
“We were able to build Carrier Warehouse in 7 months from start to finish with the help of Yantis. Lets do it again!”– Brett Shirley, Peinado-Shirley Construction
About Yantis Company
- Senior Management
- Our History
- Why work with Yantis?
- Career Opportunities
- Safety Program
Our Services
- Commercial / Industrial
- Single Family Developments
- Asphalt Maintenance
- Public Infrastructure
- Rock Milling / Trenching
- Curb / Concrete Division
Our Services
Copyright 2018 Yantis Company, All Rights Reserved.